This project required demolition of the former shop premises situated on South Henry St and Botchergate. For the purpose of the demolition road closure to south henry street had to be put in place and a permit from the council had to be granted for us to use some council land for welfare facilities. We are very diverse and always ensure we work along side local autorities as much as possible, so the works can be carried out safely. The works required phased scaffolding erecting to both South Henry Street and Botchergate, the works where carried out by a registered scaffold company.
Tree and vegetation clearance was required at site, Asbestos containing materials was removed. Deconstruction of the former shops down to ground level. Remedial works to the party walls. All waste materials arising was removed off site to a licensed waste transfer facility.
Before any demolition works took place, a full inspection of the site was undertaken.