Camelot Theme Park
Camelot theme park was a substantial job that required a lot of Demolition to various structures, single storey of wood and some brick construction. Some of the buildings where made of Portal Steel Frame construction with metal clad sheeting and mock stone/brick render works. The site was carried out in two areas as there was a considerable level changes and natural woodland between the two. Any works we carry out, are always designed to ensure the minimum impact to the surrounding natural areas is achieved. Within the works at Camelot some buildings required because bats where inhabiting in them, these where marked on the plans and where addressed in the second phase. All buildings and above ground structure where taken down to slab ground level. All construction waste was carefully disposed off site to a licensed waste transfer facility. Brick and concrete hardcore materials to be stockpiled in two locations .Phase 1 works at Camelot Theme park where completed in 12 weeks, and we are due to go back on site for phase 2 in January 2022.