Former Williams bodyshop was situation near Wrexham.
GM Demolition were appointed to complete the work.
The project to 14 Months.
Firstly we carried out the removal of the tin sheets, roofing and side sheets cement asbestos. All work was undertaken prior to the demolition commencing.
Cut down of the building using an excavator was required with a steel shear. Removal of all hard standing, floor slabs and foundations and all arising materials crushed.
A full remediation of the ground was undertaken and all contaminated materials were taken to a licensed tip.